A1 Blaydon Haughs Viaduct
Mechanical Movement Joint
Refurbishment of two, six element mechanical expansion joints has now been
completed on the A1 trunk road bridge over the River Tyne. This was the first
project of a new joint venture between USL BridgeCare and RW Engineering group.
The joints were originally supplied in 1989 by RWE subsidiary RW Sollinger
Hutte; they were installed on the A1 blaydon haughs viaduct in Gateshead, Tyne
and Wear, a stretch of road managed by A-One for the highways Agency, who are
responsible for this stretch of the trunk road. The new joint venture with the
manufacturer RW-SH will all USL BridgeCare division to extend its service and
product portfolio.
This scheme required the design and fabrication of two special temporary
lamellae suitable to be dropped into the joint in order to carry traffic loads,
and develop the dismantling and assembly techniques to ensure the work could be
carried out in a series of limited working hours overnight carriageway
closures.
The project started on the 3rd September 2005 was completed well within the
initially allotted 12 week period. The scope of work started with the initial
removal of the concrete from around the joints. The following stages of work
included the various stages of dismantling the joint, all of which was done
from underneath the joint in the expansion cavity while the carriageway was
fully closed.
This closure allowed full access for a 30 tonne crane that is
needed to remove the existing 12.2 metre long lamella and replace with the
specially fabricated temporary works or repaired lamella. These lamellae each
have an approximate weight of one tonne. This work is done in a sequence that
meant the there was sufficient lamellae whether old, repaired or temporary
fixed into place so that the carriageway could be kept open during periods of
repair.
In order to complete the repairs to the lamellae and keep the bridge open
outside of the times of on-site operations the two temporary lamellae were
utilised. The lamellae were then transported to an off site fabrication
facility and carefully inspected in order to fully assess the extent of the
work needed to each, allowing repairs of each element comprehensive. All weld
positions between the lamella and saddles, which sit on the guide bars, were
gouged to remove existing weld and fatigued metal around the crack. RW-SH coded
welders from Germany then built back the repair. In one case a 2500mm length of
80 by 80mm Type EN1024 steel was cut out and replaced with new due to the
extent of the defects.
All weld repairs are inspected and tested by A-ONE's representative from
Sandberg's before the complete lamella is released for shot blasting and
factory painting with a 3 coat epoxy/MIO/polyurethane system to the Highways
Agency specification. By mid October the north bound carriageway had been
reassembled using only seven carriageway closures with all work being completed
well within each permitted closure times including new replacement seals and,
with the south bound carriageway completed by mid November. Further work is
carried out to replace the bearings and pads though all from below while the
traffic flows above. All parties agree this solution and methodology for repair
will ensure the in-service life of the joint for the foreseeable future though
provision has been made for detailed inspections and possible replacement of
PTFE bearings 5-7 years after completion.
USL's joint venture with RWE is intended to allow USL BridgeCare to increase
its ability to cater for the more demanding needs of the bridge engineering
industries. Incorporating the expertise and renowned quality of the RWE joint
and bearing systems complimenting the service and product range already offered
by USL into a more complete package. This venture will increase USL
BridgeCare's ability to cater for the more demanding needs of the bridge
engineering industry. The A1 Blaydon project has confirmed collaboration is
capable of operating in an extremely effective manner, catering for the needs
of the individual client, whilst also benefiting both parties creating a strong
alliance to meet any future demand for similar projects.
The partnership between USL and RW-SH will work as it has on the A1 Blaydon
Haughs Viaduct project, with RW-SH supplying specialist parts as well as
providing skilled labour. USL BridgeCare will work alongside RW-SH on site to
provide necessary local support, whilst also acting in a project management and
consultancy role to liaise with clients. The primary geographic focus for this
partnership is in the UK and Ireland, largely in part to USL BridgeCare's
expert local understanding of the requirements of Highway Agencies and the
demands of the customers within this area.
For further information on
BridgeCare products
click here
Alternatively fill in our
enquiry form, call
+44 (0) 191 416 1530, fax
+44 (0) 191 415 4377
or email
info@usluk.com
BACK
|